Step 7:
A: Before working NO.1 and NO.2 must be loose ,machine no pressure .
B—. First addjust NO.2 , make pressure at 5-10Mpa (5-10兆帕)
C—.Second adjust NO.1 , make the pressure at 30Mpa (pressure need below 32Mpa) .
D. After working N0.1 and NO.2 must loose , no pressure .
All machine flow explain :
1. connnet pipe , inlet and ourlet pipe .
2. open top put oil into machine .(Diesel machine use oil is ok )
3.check oil in middle is ok .
4. connet water pipe , small pipe is ok , if machine little hot , will take hot go out .
5. connet machine power
6. checking machine running way , need righ way .
7. Adjust working pressure .